The project is implemented by the Georgian State Electricity Systems (GSE) and the objective is to construct the 220 kW Substation Nenskra, OTL 110 kW Mestia-Nenskra, OTL Nenskra-Jvari 500 kW.  The role of the Gergili LLC was to develop Environmental Impact Assessment (EIA) reports for 220 kW Substation Nenskra, 110 kW Overhead Transmission Line Mestia-Nenskra and OTL Nenskra-Jvari 500 kW in accordance with national legislation.

 

Start Date: 2018

End Date: 2019

Country: Georgia

Client: Georgian State Electricity Systems

Origin of Funding: Georgian State Electricity Systems